Schedule
| Permits | |
| Trench-Set Forms | |
| Plumbing- Rough/Inspection | |
| Concrete- Slab Preparation | |
| Termite Pretreat/Foundation Inspection | |
| Pour Slab | |
| Utility Trenching | |
| Pour Flatwork | |
| Frame Walls | |
| Trusses Delivered | |
| Sheetmetal Chase Top | |
| Frame Roof/Roof Nail Inspection | |
| Fireplace Set | |
| Plumbing – Top Out | |
| HVAC Rough In/Gutters | |
| Electric Wiring Rough-In | |
| Roof Material | |
| Paint – Fascia | |
| Windows Installed | |
| Exterior Doors Delivered/Set | |
| Frame Walk with Family | |
| Insulation Batts/Inspection | |
| Sheetrock/Nail/Inspection | |
| Clean – Sheetrock | |
| Stucco | |
| Sheetrock – Tape & Texture | |
| Garage Door Install | |
| Insulation – Blow In | |
| Set Cabinets & Trim | |
| Paint Interior/Exterior | |
| Downspouts | |
| Roof Trim | |
| Countertops | |
| Fireplace Surround & Hearth | |
| HVAC Finish | |
| Appliance Delivery | |
| Electric Finish | |
| Vinyl | |
| Plumbing Finish | |
| Carpet | |
| Finish Hardware | |
| Construction Clean | |
| Mirrors/Shower Doors | |
| Fireplace Doors | |
| Paint Touchup | |
| Envision Homes Pre-Home Demonstration | |
| Detail Punch List | |
| Final Clean | |
| Final Inspection |

Driveway had to be widened and leveled in order to allow access to the homesite. (Family was living on site in trailers seen here, provided by FEMA.)

Rocks had to be crushed and removed to make room for the new foundation.