Schedule

Permits Completed
Trench-Set Forms Completed
Plumbing- Rough/Inspection Completed
Concrete- Slab Preparation Completed
Termite Pretreat/Foundation Inspection Completed
Pour Slab Completed
Utility Trenching Completed
Pour Flatwork Completed
Frame Walls Completed
Trusses Delivered Completed
Sheetmetal Chase Top Completed
Frame Roof/Roof Nail Inspection Completed
Fireplace Set Completed
Plumbing – Top Out Completed
HVAC Rough In/Gutters Completed
Electric Wiring Rough-In Completed
Roof Material Completed
Paint – Fascia Completed
Windows Installed Completed
Exterior Doors Delivered/Set Completed
Frame Walk with Family Completed
Insulation Batts/Inspection Completed
Sheetrock/Nail/Inspection Completed
Clean – Sheetrock Completed
Stucco Completed
Sheetrock – Tape & Texture Completed
Garage Door Install Completed
Insulation – Blow In Completed
Set Cabinets & Trim Completed
Paint Interior/Exterior Completed
Downspouts Completed
Roof Trim Completed
Countertops Completed
Fireplace Surround & Hearth Completed
HVAC Finish Completed
Appliance Delivery Completed
Electric Finish Completed
Vinyl Completed
Plumbing Finish Completed
Carpet Completed
Finish Hardware Completed
Construction Clean Completed
Mirrors/Shower Doors Completed
Fireplace Doors Completed
Paint Touchup Completed
Envision Homes Pre-Home Demonstration Completed
Detail Punch List Completed
Final Clean Completed
Final Inspection Completed

osmos gallery image

Driveway had to be widened and leveled in order to allow access to the homesite. (Family was living on site in trailers seen here, provided by FEMA.)

osmos gallery image

Rocks had to be crushed and removed to make room for the new foundation. 

 osmos gallery image

osmos gallery image

  osmos gallery image

 osmos gallery image

 osmos gallery image